Construction Updates – May 13, 2014

20141121_ActiveWorkSites

Please be informed that the contractor will be in the neighborhood paving streets (Phillips Ave., Kathy Kt., Burton Ave., and Adelpha Ave.) and driveway approaches starting on Wednesday, May 13, and running through the end of the week.  This schedule could change if rain causes delays.  We apologize for this disruption and will do our best to accommodate any special needs.

  • Please understand that there will be delays in accessing the area at various points in the process while the asphalt is placed and cooling. It can be up to four hours before vehicles are permitted to drive on the freshly laid pavement.
  • The schedule describing which streets will be paved on which days has not yet been finalized; however, the contractor will be paving the asphalt approaches (the driveway areas adjacent to the street), before paving the roads.
  • If you have an asphalt approach and you will need your car during the day, we recommend that you have your vehicles out of your driveway before 7 a.m. on Wednesday morning and that you park off your street.
  • On Thursday and Friday, vehicles should be parked away from the work area to avoid getting them trapped on the site by 7a.m.  During the day, you may not be able to get to your driveway.  If you need your car during the day, please park off your street.

Repaving the road is the last major phase of the project.  As always, we appreciate your patience as things are wrapping up.  Minor restoration, including placement of road shoulders, top soiling, seeding, and other items will still occur after paving the road.

Thank you for your continued patience and support.  If you have any questions, concerns, or special circumstances, please contact us.

Spicer Group, Inc.                                                   
James Ensign, Project Engineer                                 Cell (989) 493-0997

Drain Commissioner’s Office                            Office (517) 676-8395
Angie Cosman, Project Coordinator                          Cell (517) 719-5431

Advertisements
Posted in Uncategorized

Construction Updates – Nov. 24-29, 2014

Active Work Sites

Active Work Sites

 

Snow accumulating onsite.

Snow accumulating onsite.

This week, the contractor will be placing the gravel shoulders and gravel sidewalk ramps along Burton, Adelpha, Phillips, and Kathy Kourt and performing general restoration and project cleanup tasks.  After this week, the contractor will be shutting down for the winter and will only be onsite to perform maintenance tasks.

Along Burton, Adelpha, Phillips, and Kathy Kourt the contractor has installed asphalt wedges at driveway approaches and at manhole structures.  Please be mindful of these elevated wedges as you drive along these roads.

The contractor has installed the ADA sidewalk ramps on Dean and Auburn but the sidewalk ramps on Burton, Adelpha, Kathy Kourt, or Phillips won’t be installed until next Spring when the final layer of asphalt is placed on the road.  For the winter, the contractor will level the ramps and place gravel as a temporary walkway.  Please be mindful that the walk surface may be more rough than the sidewalks.

The contractor will be removing the “Road Closed” signs from the project site and all roads will be reopened to thru traffic.

We hope that you have a wonderful Thanksgiving holiday this week as you spend time with your loved ones.

Posted in Uncategorized

Construction Updates – Nov. 17-22, 2014

Active Work Sites

Active Work Sites

 

2014-11-13 14.11.14The contractor will be preparing the project site for the winter.  This will include wedging asphalt around manholes on Burton, Adelpha, Phillips, and Kathy Kourt.

The restoration crew will be working throughout the project site cleaning up various items including placing topsoil along driveway edges, constructing gravel driveways, installing mailboxes, and general project cleanup.

Dean and Auburn Avenues will remain closed to thru traffic from Richard Street to Holt Road and Phillips, Adelpha, and Burton Avenues will be closed to thru traffic from Kathy Kourt as the contractor completes this restoration work.  We appreciate the public’s patience as you avoid this construction zone.

Posted in Uncategorized

Construction Updates – Nov. 10-15, 2014

Active Work Sites

Active Work Sites

 

Burton Avenue being graded prior to paving

Burton Avenue being graded prior to paving

The contractor will be working throughout the whole project area. Please note that the following construction schedule is subject to weather delays.

The contractor will continue to grade Adelpha Avenue to prepare for paving.

The contractor will be paving asphalt throughout the project site as weather allows. Rain and severe cold weather will inhibit paving.

The restoration crew will be working along Kathy Kourt and Adelpha Avenue placing topsoil and shaping infiltration swales and restoring the rear lot area behind Phillips Avenue.

During the second half of the week, the contractor will be seeding swales along Adelpha Avenue, placing the gravel shoulders along Dean, Auburn, and Richard, and cleaning up topsoil along driveway approaches and the gravel shoulders.  The contractor will also be installing concrete ADA ramps for the sidewalks along Richard at Dean and Auburn Avenues and other miscellaneous concrete at other locations around the project site.  Lastly, gravel drives along Dean, Auburn, and Richard will be restored.

Dean and Auburn Avenues will remain closed to thru traffic from Richard Street to Holt Road and Phillips, Adelpha, and Burton Avenues will be closed to thru traffic from Kathy Kourt as the contractor performs pipe installation, pavement pulverizing, and completes restoration work.  We appreciate the public’s patience as you avoid this construction zone.

Posted in Uncategorized

Construction Updates – Nov. 3-8, 2014

Active Work Sites

Active Work Sites

 

Rear lot area behind Burton Avenue.

Rear lot area behind Burton Avenue.

The contractor will be working throughout the whole project area. Please note that the following construction schedule is subject to weather delays.

The pulverizing of the existing pavement on Burton, Adelpha, Phillips, and Kathy Kourt is scheduled for this Thursday the 6th.  Paving of the top course on Auburn, Dean, and Richard is scheduled for next week but the schedule may change depending on contractor availability.

The concrete crew will be installing forms and pouring sidewalk and driveway approaches along Adelpha Avenue.

The restoration crew will be working behind the pipe and concrete crews shaping infiltration swales and placing the topsoil on Adelpha Avenue and restoring the rear lot areas along Phillips and Burton Avenues and in the Family Video Detention Basin.

Dean and Auburn Avenues will remain closed to thru traffic from Richard Street to Holt Road and Phillips, Adelpha, and Burton Avenues will be closed to thru traffic from Kathy Kourt as the contractor performs pipe installation, pavement pulverizing, and completes restoration work.  We appreciate the public’s patience as you avoid this construction zone.

Posted in Uncategorized

Construction Updates – Oct. 27-Nov. 1, 2014

Active Work Sites

Active Work Sites

 

20141023_162158The contractor will be working throughout the whole project area. Please note that the following construction schedule is subject to weather delays.

The contractor will be preparing to pave the top course layer of asphalt on Auburn, Dean, and Richard.

A pipe crew will be working in the rear lot area behind Burton Avenue. Pipe installation is wrapping up on Adelpha Avenue, with sidewalks and restoration following close behind.

Dean and Auburn Avenues will remain closed to thru traffic from Richard Street to Holt Road and Phillips, Adelpha, and Burton Avenues will be closed to thru traffic from Kathy Kourt as the contractor performs paving preparation and completes restoration work.  We appreciate the public’s patience as you avoid this construction zone.

Posted in Uncategorized

Construction Updates – Oct. 20-25, 2014

Active Work Sites

Active Work Sites

2014-10-16 14.56.58The contractor will be working primarily on the east side of the project area.  Please note that the following construction schedule is subject to weather delays.

The contractor will be preparing the west side to receive the top course of asphalt.  The paving will be done in 1-2 weeks.

One pipe crew will be working in the rear lot area north of Kathy Kourt.  A second pipe crew is planning to move to Adelpha Avenue during the week.

The restoration crew will be working behind the pipe and concrete crews shaping infiltration swales and placing the topsoil on Kathy Kourt and sand on Phillips Avenue.

Dean and Auburn Avenues will remain closed to thru traffic from Richard Street to Holt Road and Phillips, Adelpha, and Burton Avenues will be closed to thru traffic from Kathy Kourt as the contractor performs pipe installation, paving operations, and completes restoration work.  We appreciate the public’s patience as you avoid this construction zone.

 

 

Posted in Uncategorized

Construction Updates – Oct. 13-18, 2014

Active Work Sites

Active Work Sites

 

The contractor will be working throughout the whole project area. Please note that the following construction schedule is subject to weather delays.

2014-10-08 16.38.19The contractor will continue to grade Auburn, Dean, and Richard and will begin paving in the middle of the week.

One pipe crew will be working in the rear lot area north of Kathy Kourt. This crew should be moving to Adelpha Avenue by the end of the week.

The concrete crew will be installing forms and pouring sidewalk and driveway approaches along the east side of Phillips Avenue.

The restoration crew will be working behind the concrete crew shaping infiltration swales and placing the topsoil on Burton, Kathy Kourt, and Phillips.

Dean and Auburn Avenues will remain closed to thru traffic from Richard Street to Holt Road and Phillips, Adelpha, and Burton Avenues will be closed to thru traffic from Kathy Kourt as the contractor performs pipe installation, pavement pulverizing, and completes restoration work.  We appreciate the public’s patience as you avoid this construction zone.

Posted in Uncategorized

Construction Updates – Oct. 6-11, 2014

Active Work Sites

Active Work Sites

 
IMG_2366The contractor will be working throughout the whole project area. Please note that the following construction schedule is subject to weather delays.

Two pipe crews will continue to install storm sewer pipe.  One pipe crew will be working in the Burton Avenue area.  The other pipe crew will continue to install storm sewer on the north portion of Phillips Avenue and will be moving to Adelpha Avenue when the Phillips Avenue storm sewer is complete.

The concrete crew will be installing forms and placing 2014-09-29 11.09.35concrete sidewalk and concrete driveway approaches along the East side of Burton Avenue.

The restoration crew will be working behind the pipe and concrete crews shaping infiltration swales and placing the topsoil.

In the middle of the week, the contractor will begin preparing to repave Richard Street, Dean Avenue, and Auburn Avenue. The contractor will begin by crushing and shaping the existing asphalt road.

Dean and Auburn Avenues will remain closed to thru traffic from Richard Street to Holt Road and Phillips, Adelpha, and Burton Avenues will be closed to thru traffic from Kathy Kourt as the contractor performs pipe installation, pavement pulverizing, and completes restoration work.

We appreciate the public’s patience as you avoid this construction zone.

Posted in Uncategorized

Construction Updates – Sept 29-Oct. 4, 2014

Active Work Sites

Active Work Sites

 

IMG_2366The contractor will continue work on Auburn Avenue, Phillips Avenue, Burton Avenue and Kathy Kourt. Please note that the following construction schedule is subject to weather delays.  Two pipe crews will continue to install storm sewer pipe.  One pipe crew will continue to install storm sewer on the north portion of Phillips Avenue while the second pipe crew will continue to install storm sewer on Burton Avenue.

The concrete crew will be installing forms and continuing to place concrete on Burton Ave. during the first part of the week.

The restoration crew will begin work on Richard Street and Kathy Kourt shaping infiltration swales and placing the topsoil. The restoration crew will also be performing restoration work along Burton Ave. behind the concrete work.

Lastly, the contractor will be installing a new outlet structure and trash rack to improve flow through the Diehl Consolidated Drain in the park at Tolland Avenue and Wemple Street.

Auburn, Phillips and Burton Avenues will remain closed to thru traffic north of Holt Road as the contractor performs pipe installation and completes restoration work.  We appreciate the public’s patience as you avoid this construction zone.