Construction Updates – Nov. 24-29, 2014

Active Work Sites

Active Work Sites

 

Snow accumulating onsite.

Snow accumulating onsite.

This week, the contractor will be placing the gravel shoulders and gravel sidewalk ramps along Burton, Adelpha, Phillips, and Kathy Kourt and performing general restoration and project cleanup tasks.  After this week, the contractor will be shutting down for the winter and will only be onsite to perform maintenance tasks.

Along Burton, Adelpha, Phillips, and Kathy Kourt the contractor has installed asphalt wedges at driveway approaches and at manhole structures.  Please be mindful of these elevated wedges as you drive along these roads.

The contractor has installed the ADA sidewalk ramps on Dean and Auburn but the sidewalk ramps on Burton, Adelpha, Kathy Kourt, or Phillips won’t be installed until next Spring when the final layer of asphalt is placed on the road.  For the winter, the contractor will level the ramps and place gravel as a temporary walkway.  Please be mindful that the walk surface may be more rough than the sidewalks.

The contractor will be removing the “Road Closed” signs from the project site and all roads will be reopened to thru traffic.

We hope that you have a wonderful Thanksgiving holiday this week as you spend time with your loved ones.