Construction Updates – Nov. 3-8, 2014

Active Work Sites

Active Work Sites

 

Rear lot area behind Burton Avenue.

Rear lot area behind Burton Avenue.

The contractor will be working throughout the whole project area. Please note that the following construction schedule is subject to weather delays.

The pulverizing of the existing pavement on Burton, Adelpha, Phillips, and Kathy Kourt is scheduled for this Thursday the 6th.  Paving of the top course on Auburn, Dean, and Richard is scheduled for next week but the schedule may change depending on contractor availability.

The concrete crew will be installing forms and pouring sidewalk and driveway approaches along Adelpha Avenue.

The restoration crew will be working behind the pipe and concrete crews shaping infiltration swales and placing the topsoil on Adelpha Avenue and restoring the rear lot areas along Phillips and Burton Avenues and in the Family Video Detention Basin.

Dean and Auburn Avenues will remain closed to thru traffic from Richard Street to Holt Road and Phillips, Adelpha, and Burton Avenues will be closed to thru traffic from Kathy Kourt as the contractor performs pipe installation, pavement pulverizing, and completes restoration work.  We appreciate the public’s patience as you avoid this construction zone.