Construction Updates – Oct. 20-25, 2014

Active Work Sites

Active Work Sites

2014-10-16 14.56.58The contractor will be working primarily on the east side of the project area.  Please note that the following construction schedule is subject to weather delays.

The contractor will be preparing the west side to receive the top course of asphalt.  The paving will be done in 1-2 weeks.

One pipe crew will be working in the rear lot area north of Kathy Kourt.  A second pipe crew is planning to move to Adelpha Avenue during the week.

The restoration crew will be working behind the pipe and concrete crews shaping infiltration swales and placing the topsoil on Kathy Kourt and sand on Phillips Avenue.

Dean and Auburn Avenues will remain closed to thru traffic from Richard Street to Holt Road and Phillips, Adelpha, and Burton Avenues will be closed to thru traffic from Kathy Kourt as the contractor performs pipe installation, paving operations, and completes restoration work.  We appreciate the public’s patience as you avoid this construction zone.

 

 