Construction Updates – Sept 08-14, 2014

Active Work Sites

Active Work Sites

 

2014-09-04 16.04.52This week the contractor is working on Auburn Avenue and Kathy Kourt.  One pipe crew continues to install storm sewer on Auburn Avenue, while the second pipe crew is on Kathy Kourt installing storm sewer on the north side of the street.  The concrete crew is also scheduled to return to the site in the middle of the week to finish the sidewalk on the west side of Auburn and pour any concrete approaches in this area.  The restoration crew is continuing behind the pipe crew on Auburn shaping infiltration swales and placing the topsoil.

Both Dean and Auburn Avenues will remain closed between Richard Street and Holt Road as the contractor wraps up the work in this area.  We appreciate the public’s patience as you avoid this construction zone.

Advertisements