Construction Updates – Sept 01-06, 2014

Active Work Sites

Active Work Sites

2014-08-29 10.35.54This week the contractor is working on Dean Avenue, Richard Street, Auburn Avenue, and Kathy Kourt.  Concrete sidewalks will be poured along the South side of Richard Street and along the West side of Auburn Avenue.  Seeding and mulching of the infiltration swales is being performed on Dean Avenue.  One pipe crew continues to install storm sewer on Auburn Avenue, while the second pipe crew is on Kathy Kourt installing storm sewer east to Burton Avenue.

Both Dean and Auburn will remain closed north of Richard Street as the contractor wraps up the work in this area.  We appreciate the public’s patience as you avoid this construction zone.